The reconstruction of AC Road enters the final phase

The reconstruction of AC Road enters the final phase

0:00

Construction of the Pallathuruthy bridge along the Alappuzha-ChanganasSery road in Progreso. | Photo credit: Suresh Alleppey

The reconstruction of the Alappuzha-Changanassery road (AC) has entered its final phase. According to the Kerala State Transportation project (KSTP), almost all the main works have been completed, except the Pallathuruthy bridge.

According to the original plan, the project, with the aim of avoiding the flood of the road during the Monzón season, was scheduled for its completion in 2023. However, the government extended the deadline. The project was mainly delayed due to the time that the Government took to approve the revised estimate for the construction of a parallel bridge in Pallathuruthy.

The road of 24.14 km is being rebuilt at a cost of ₹ 671.66 million rupees under the Kerala reconstruction initiative. “Work is progressing quickly with the aim of completely opening the way in three to four months. When the project is completed, the final cost is expected to touch ₹ 880.72 million rupees, ”said a KSTP official.

The project includes the construction of four main bridges, five semi -said high steps, 14 minor bridges, three roads and 64 sewers, among other works. The authorities said that, in addition to the final touches, all the other work in the Kinangara, Nedumudi and Muttar bridges had been completed. In the case of the Pallathuruthy bridge, approximately 60% of the work had been completed.

Five high steps have been opened in Pandarakalam, Nazareth Junction, Jyothi Junction, Mankombu and Onnamkara. Similarly, all small bridges, roads and sewers have opened. The road surface is also about to finish, with 98% of the work that dense bituminous macadam uses and 90% of the finished bituminous concrete work. In addition, 99% of the land leveling work of more than 7 km has been completed.

The two -lane road with trails has a width of 13 meters. Acaad’s work is being carried out by a joint business of the Cooperative Society of the Uralungal and Evrascon labor contract.

Releated Posts

Defense Minister, Rajnath Singh, has telephone conversations with us, Hegseth

0:00 Rajnath Singh Defense Minister. Archive Defense Minister Rajnath Singh, and his American counterpart Pete Hegseth on Thursday…

ByByAmlanFeb 6, 2025

The locals attack the Police Station after the man dies in police custody in Muzaphapur

0:00 The tension prevailed in Kalwari’s village in the Muzampharpur de Bihar district after a man died in…

ByByAmlanFeb 6, 2025

Woman withdrawn deceived from ₹ 8.13 Lakh with 100% loan promise for the project

0:00 The business trip of a 58 -year -old retired woman reached an obstacle before she could leave.…

ByByAmlanFeb 6, 2025

HBALLAVER DE HEBBAL will be open to the public in May 2025

0:00 The work in the additional loop for the high passage of Hebbal must be completed before April…

ByByAmlanFeb 6, 2025
Scroll to Top